Construction Traffic Management Plans (CTMP).
Outline and full Construction Traffic Management Plans that get conditions discharged and keep the site running, from small infill to solar and energy schemes.
Also known as: CTMP, Construction Traffic Management Plan, Outline Construction Traffic Management Plan, outline CTMP, construction traffic, construction management, construction traffic management, Construction Management Plan, Construction Method Statement
What’s included.
Most schemes need a CTMP, often as an outline at planning stage and a full plan before work starts. National policy makes clear the highways tests apply during construction as well as once a scheme is built.
- Construction vehicle routes and restrictions
- Delivery numbers, timing and booking
- Site access, swept paths and wheel washing
- Contractor parking and compound layout
- Temporary traffic management
- Communication with neighbours and monitoring
Straightforward, proportionate, agreed early.
Outline then full
An outline CTMP sets the principles for planning. The full CTMP is finalised with the contractor before work starts.
Workable
Routes and timings the contractor can actually stick to.
Neighbour-aware
Measures that reduce disruption, which reduces complaints and enforcement.
Other names for this work
CTMPs are also called Construction Management Plans (CMP), construction method statements or construction traffic plans. Councils use different names in their conditions, but they usually want the same information.
What the application usually needs
- Construction vehicle routes and any roads to avoid.
- Delivery numbers by phase and the hours they will arrive.
- Site access, swept paths and wheel washing.
- Contractor parking and the compound layout.
- Temporary traffic management and footway protection.
A typical case
A typical case is a solar farm reached by rural lanes. The council asks for an outline CTMP with the application and a full CTMP before work starts. We estimate deliveries by phase, agree a route avoiding a village centre, design passing places and a temporary access, propose a condition survey of the route before and after construction, and set out how abnormal loads will be managed. The contractor adopts the plan and updates it before mobilising.
Standards and method
A CTMP sets out the construction programme, vehicle types and numbers, routes, hours, site access and measures to protect people walking and cycling. For larger schemes it includes a condition survey of the route, a delivery booking system and a named contact for complaints. Abnormal loads such as transformers or cranes are planned separately with the haulier and notified through ESDAL.
In London and some cities a Construction Logistics Plan following Transport for London’s guidance is used instead.
When the highway authority comes back
Concerns usually relate to routes through villages, delivery timing near schools and damage to verges. A clear routing plan, delivery hours that avoid school times and a pre-start condition survey usually resolve them.
Questions we get asked
What is the difference between an outline and a full CTMP?
An outline CTMP sets the principles at planning stage. A full CTMP adds the contractor’s detail and is usually needed before work starts.
Is a CTMP the same as a Construction Logistics Plan?
They overlap. CLPs follow Transport for London’s guidance and are common in London and some cities. CTMPs are the usual term elsewhere.
Can you discharge a CTMP condition?
Yes. Send us the decision notice and the contractor’s details.
Is a Construction Management Plan the same as a CTMP?
Usually they overlap. Councils use different names, but the transport content is similar.
What is a condition survey?
A record of the state of the route before construction, repeated afterwards, so any damage caused by construction traffic can be identified.
How are construction deliveries estimated?
From the build programme, materials quantities and contractor experience, phase by phase.
Do you prepare CTMPs for solar and battery schemes?
Yes, including routing, temporary access and abnormal loads.
Often needed alongside.
Last reviewed October 2026 by Ripple Development Planning. Policy and guidance change; for advice on a specific site, send us the details.