Agreements and approvals

Section 278 agreements.

Getting Section 278 highway works from planning consent to completion: scope, design, approval and the agreement, with fewer surprises on cost and programme.

Also known as: Section 278, S278, Section 278 agreement, highway works agreement

Illustration of a zebra crossing with belisha beacons, dropped kerbs and red tactile paving, with a wheelchair user crossing
Typical Section 278 works: a crossing, dropped kerbs, tactile paving and footway links.
What we do

What’s included.

A Section 278 agreement under the Highways Act 1980 allows a developer to carry out works on the existing public highway, such as a new access, footway or junction improvement. The highway authority approves the design, charges fees and requires a bond.

  • Scope of works from the planning consent
  • Preliminary and detailed design coordination
  • Road Safety Audits
  • Technical approval
  • Fees, bonds and commuted sums
  • Liaison through construction and handover
How we approach it

Straightforward, proportionate, agreed early.

Know the scope early

Off-site works defined at planning stage, so costs are known before you commit.

Consistent

The S278 design follows what planning approved, so nothing goes back to committee.

Kept moving

Prompt responses to the council, because S278 delays hold up occupation.

Also searched as

Other names for this work

Section 278 agreements are also called S278 agreements, highway works agreements or off-site highway works. Smaller accesses may instead need a Section 184 licence or vehicle crossover approval.

What it involves

What the application usually needs

  • A clear scope of off-site works, drawn from the planning permission.
  • Preliminary design, then detailed design for technical approval.
  • Road Safety Audits at the stages the highway authority requires.
  • Any traffic regulation orders, street lighting or drainage changes.
  • Coordination with the contractor through construction and completion.
In practice

A typical case

A typical case is a housing scheme with a planning condition requiring a new junction and a footway link before occupation. We set out the scope from the approved drawings, prepare the preliminary and detailed design with the engineer, arrange the Stage 2 Road Safety Audit and submit for technical approval. Once the agreement is in place, the works are built by an approved contractor, inspected by the highway authority and signed off, with a Stage 3 audit at completion.

Technical points

Standards and method

The process usually runs in this order: scope of works, preliminary design, technical approval of the detailed design, the legal agreement, construction, inspection and completion. Each highway authority sets its own procedure and timescales, so we confirm these early. A traffic regulation order may be needed for new waiting restrictions or speed limits, and has its own consultation period.

Simple vehicle accesses are often dealt with under Section 184 of the Highways Act 1980 or a vehicle crossover application instead. We advise which route applies.

FAQ

Questions we get asked

What is the difference between Section 278 and Section 38?

Section 278 covers works to the existing highway. Section 38 covers new roads that the council will adopt.

How long does a Section 278 agreement take?

Often several months, depending on the council and the complexity. Starting early is the best way to keep it off the critical path.

What are commuted sums?

Payments some councils require for maintaining non-standard materials or features in the future.

What is a Section 278 agreement?

A legal agreement under the Highways Act 1980 that allows a developer to carry out works on the existing public highway.

What is the difference between Section 278 and Section 184?

Section 184 typically covers simple accesses across a footway or verge. Section 278 covers larger works such as junctions, footways and crossings.

When should the Section 278 process start?

As soon as the scope is known, often straight after planning permission, because design approval and the agreement take time.

Do you design the Section 278 works?

We prepare the transport and highway design and work with civil engineers on drainage, lighting and construction details.

Related

Often needed alongside.

Transport planning A to Z

Last reviewed October 2026 by Ripple Development Planning. Policy and guidance change; for advice on a specific site, send us the details.